Example Asbestos Removal Projects in Tigard

Each example runs from the first test or survey through the removal steps, the days on site and about what the job would cost.

Outside survey of an apartment building before every balcony is rebuilt

Example project

Building
1970s two-story apartment building in Durham, 24 units, each with a wood balcony and a sliding door
Original request
Rebuild every balcony and replace the sliding doors, with tenants staying home
Testing
About 20 samples of the siding, the balcony coating, the soffits, the door caulk and the flashing tape
Found
Asbestos in the caulk around the sliding door frames
Clear
No asbestos in the siding, the balcony coating, the soffits or the flashing tape
Timeline
Two sampling days around the tenants' schedules, then the report the next week
Estimated survey cost
$2,200

Scope of work

A survey of the outside materials the balcony and door work will disturb, about 20 samples, lab results for each layer and a written report. Removing the positive caulk is priced separately.

Project overview

In this example, the owner of a 24-unit building from the 1970s in Durham plans to rebuild every balcony and put in new sliding doors. The carpenters will cut siding, soffits and old caulk where each balcony meets the wall, and a building of five or more units is surveyed before renovation whatever its age.

Only the caulk around the sliding door frames tests positive. It is removed door by door ahead of the carpenters, and the rest of the balcony work goes ahead as ordinary construction.

The goal

The goal is a balcony project with one known positive material, cleared before the carpenters cut anything.

Process

  1. Planning The carpenters mark where each balcony and door will be cut.
  2. Sampling days About 20 samples taken from a handful of typical balconies.
  3. About a week later Lab results and a report locating the positive caulk.
  4. Then The caulk comes out door by door, ahead of the balcony crew.

Planning right

  • Survey the outside of a building before rebuilding balconies, not only the inside.
  • Tell tenants when someone will be on their balcony.
  • A slider replaced years later is sampled separately.
  • Post the report where the carpenters and the caulk crew can read it.

Get a free quoteMore about asbestos testing and surveys

Textured ceiling scraped from between the exposed beams of a living room

Example project

Home
1960s one-story house in King City with exposed beams across the living room ceiling
Original request
Smooth ceilings between the beams, with the beams kept and refinished
Testing
Three samples from different bays; every one positive
Area
About 240 sq ft of ceiling in eight bays between the beams
Work
Living room enclosed under negative air after the notice period, each bay wetted and scraped
Timeline
Ten-day notice, then two working days
Cost
$3,300

Scope of work

Samples of the texture, the friable notice to DEQ, the living room sealed under negative pressure, the beams wrapped in plastic, the texture wetted and scraped bay by bay into double bags, the beam edges cleaned by hand, a HEPA clean and the haul. The new ceiling finish and refinishing the beams are extra.

Project overview

In this example, the owners of a 1960s house in King City want to keep the exposed beams across the living room and smooth the textured ceiling between them. The texture runs into every corner where a beam meets the ceiling.

The texture tests positive. The crew wraps the beams, scrapes each bay wet and cleans the beam edges by hand, which takes longer than an open ceiling, and the beams come out ready for refinishing.

The goal

The goal is bare ceiling bays between clean beams, ready for a smooth finish.

Process

  1. First visit Texture sampled in three bays; the bays and the beams measured.
  2. Before work Notice filed; the living room emptied and the beams wrapped.
  3. Day one Room sealed, the first bays soaked and scraped.
  4. Day two The other bays scraped, beam edges cleaned, final clean and bags hauled.

Planning right

  • Beamed ceilings take longer than open ones, so they cost more for the same area.
  • Do not sand the beams while texture is still in the bays.
  • Ask the finisher what surface the bays should be left in.
  • Texture in the hall is sampled on its own if that ceiling is next.

Get a free quoteMore about popcorn ceiling removal

Kitchen tile and half bath sheet vinyl cleared in one visit under two notices

Example project

Home
Two-story 1970s house in Tigard with the half bath off the kitchen
Original request
One new floor through the kitchen and the half bath next to it
Testing
Samples of the kitchen tile, its adhesive, and the half bath sheet vinyl with its backing
Found
Asbestos in the kitchen tile and in the backing of the half bath sheet vinyl
Clear
No asbestos in the kitchen adhesive
Area
About 150 sq ft of kitchen tile and 70 sq ft of half bath sheet vinyl
Timeline
Both DEQ notices filed together, the ten-day wait, then two working days
Cost
$3,100

Scope of work

Every layer in both rooms tested, then two DEQ notices: nonfriable for the kitchen tile, friable for the half bath vinyl. Plastic goes up in the kitchen and a negative pressure enclosure in the half bath, the tile comes up whole and the vinyl comes up wet with its backing, and the bags leave after a HEPA clean. The new floor is extra.

Project overview

In this example, the owners of a 1970s house in Tigard want one new floor through the kitchen and the half bath beside it. The kitchen has 9-inch tile, and the half bath has sheet vinyl with a felt backing.

Both test positive, under two different rules. Whole tile is nonfriable and needs five days' notice, while an asbestos sheet vinyl backing is friable and needs ten, so both notices go in together and the crew does both rooms in one visit.

The goal

The goal is two bare floors finished in one visit, so the installer can lay one floor through both rooms.

Process

  1. First visit Every layer in both rooms sampled; the floors measured.
  2. Before work Both notices filed on the same day, and the ten-day wait sets the start.
  3. Day one Kitchen sealed, tile lifted whole and wet, the floor vacuumed and wiped.
  4. Day two Half bath sealed under negative pressure, vinyl lifted wet, final clean and bags hauled.

Planning right

  • Filing both notices together keeps the two rooms on one schedule.
  • Each layer gets its own result, so a clear adhesive says nothing about the tile above it.
  • Keep the toilet out until the half bath floor is done.
  • Ask the installer whether the floor deck needs work before ordering the new floor.

Get a free quoteMore about floor tile and sheet vinyl removal

Cement shingles taken off a side wall for a new meter and a heat pump

Example project

Home
1960s one-story Tigard house sided all around in gray cement shingles
Original request
A larger electrical service, a new meter base and a heat pump pad on the side wall
Testing
Shingles and paper sampled apart; the shingles test positive
Area
About 220 sq ft of the side wall around the meter, the panel feed and the heat pump lines
Work
Shingles misted and lifted off in whole pieces once DEQ has had five days' notice
Timeline
Five-day notice, then one working day before the electrician starts
Cost
$2,300

Scope of work

A lab test of the shingles, DEQ's nonfriable notice and plastic on the ground below. The crew mists the shingles around the meter and along the new line routes, pries them off in whole pieces and wraps them, then vacuums the wall and the soil before the load goes to a permitted landfill. Electrical work, the heat pump and new siding are extra.

Project overview

In this example, the owners of a 1960s house in Tigard add a heat pump and a car charger, which means a larger electrical service. The electrician has to move the meter base and run new lines across the side wall, through gray cement shingles.

The shingles test positive. Instead of cutting holes through them, the crew takes them off whole across the part of the wall the electrician and the heat pump installer need, and new siding goes on that wall afterward.

The goal

The goal is a bare section of wall for the new service and the heat pump, with every shingle off whole and none cut.

Process

  1. First visit Shingles and paper sampled; the electrician's layout marked on the wall.
  2. Before work Notice filed; sheeting laid along the side of the house.
  3. Work day Shingles wetted, pried off whole and wrapped, the wall and the ground vacuumed.
  4. Then The electrician sets the new meter base, and the heat pump goes on its pad.

Planning right

  • Get the electrician's layout first, so only the needed part of the wall comes off.
  • No one should cut a hole through cement shingles before a lab has seen them.
  • Plan the new siding for that wall before removal, so it is not open for long.
  • If the roof is next, it is tested and priced on its own visit.

Get a free quoteMore about siding and roofing removal

Old duct tape removed before a crawl space liner goes in

Example project

Home
1970s one-story house in Tigard over a crawl space, with the heating ducts under the floor
Original request
A sealed plastic liner over the crawl space floor and up the foundation walls
Testing
Samples of the paper tape on the duct seams, the wrap on the trunk line and the tape at the boots
Found
Asbestos in the paper tape on the seams and at 14 register boots
Clear
No asbestos in the trunk line wrap
Timeline
Ten days for the notice, two days under the house
Cost
$2,100

Scope of work

Samples of the tape and the wrap, the friable notice to DEQ, the crawl space sealed at the hatch under negative pressure, the tape wetted and removed from the seams and boots, the bare metal wiped, labeled double bags, a HEPA vacuum of the ground below the ducts and the haul. Resealing the ducts and the liner are extra.

Project overview

In this example, the owners of a 1970s house in Tigard hire a crew to lay a sealed liner over the crawl space floor. That crew will crawl under every duct to fasten the liner up the walls, and the old paper tape on the duct seams is already brittle.

The tape on the seams and at the register boots tests positive, and the wrap on the main trunk is clear. The tape comes off before the liner goes in, and the heating contractor reseals the bare seams.

The goal

The goal is a crawl space with no old tape left on the ducts, so the liner crew can work under them.

Process

  1. First visit Tape and wrap sampled; the seams and boots counted and the crawl space checked.
  2. Before work Notice filed; the heating system shut off for the work days.
  3. Two work days Hatch sealed under negative pressure, tape wetted and removed, seams wiped, the ground below vacuumed.
  4. Then The ducts are resealed, and the liner crew starts.

Planning right

  • Brittle duct tape flakes when someone brushes past it, so remove it before other crews crawl in.
  • Keep the heating off until the seams are resealed.
  • Flakes on the crawl space ground are vacuumed, not raked.
  • Ask the liner crew to wait for the final clean.

Get a free quoteMore about duct and HVAC insulation removal

House cleared of asbestos before it comes down to its foundation

Example project

Home
One-story Tigard house of about 1,300 sq ft, built in the 1970s on a crawl space
Original request
Take the house down to its foundation and build a new house on it
Testing
About 24 samples from every room and the crawl space, taken by an accredited inspector
Found
Asbestos in the ceilings, the sheet vinyl of the kitchen and both baths, and the duct tape below the floor
Clear
No asbestos in the foundation, the siding, the roofing or the wall system
Timeline
Survey, the ten-day DEQ notice, then about five days of removal
Cost
$14,000

Scope of work

Ceiling texture of about 1,100 sq ft, about 180 sq ft of sheet vinyl and the duct tape under the floor, all taken out ahead of the wrecking crew. The friable notice, labeled bags, an air check and the landfill trip are included; the survey, the demolition and any foundation work are not.

Project overview

In this example, the owners of a 1970s house in Tigard decide to build a new house on the old foundation instead of remodeling. Everything above the foundation comes down, and because the house is being demolished, the owner exemption no longer applies and the whole house is surveyed.

The ceilings, the sheet vinyl and the duct tape test positive, and the foundation is clear. The crew clears the rooms one at a time and the crawl space last, so the demolition crew can take the house down to a foundation that is ready to build on.

The goal

The goal is a house cleared of asbestos down to a clean foundation, ready for demolition and the new build.

Process

  1. Week one Rooms and crawl space surveyed; the report sizes up each positive find.
  2. Next The notice goes to DEQ, and the ten-day wait runs.
  3. Removal days Rooms sealed one at a time for the ceilings and the vinyl, then the crawl space for the duct tape.
  4. Last day Air check, the last bags hauled, and the paperwork handed over.

Planning right

  • Ask the Building Division what the demolition permit needs for your address.
  • A kept foundation is still sampled, since the new house will sit on it.
  • Clear the crawl space last, after the rooms above it are done.
  • Leave a copy of the survey with the demolition crew.

Get a free quoteMore about pre-demolition abatement